WCG DoTP APP 2023/2024
7.3.6.
Programme resource considerations
EXPENDITURE ESTIMATES
TABLE 15: Programme 3 expenditure estimates
ADJUSTED APPROPRIATION
SUB-PROGRAMME
EXPENDITURE OUTCOME
MEDIUM-TERM EXPENDITURE ESTIMATE
2019/ 2020
2020/ 2021
2021/ 2022
2022/ 2023
2023/ 2024
2024/ 2025
2025/ 2026
R THOUSAND
2 926
2 723
1 253
1 326
1 652
2 218
2 286
1 Programme Support
58 466
58 935
53 540
63 732
62 834
63 256
65 055
2 Organisation Development
People Training and Empowerment
37 020
31 580
34 159
39 626
39 625
40 013
41 380
3
People Management Practices
103 194
97 417
101 930
107 593
109 986
112 008
117 192
4
201 606
190 655
190 882
212 277
214 097
217 495
225 913
Total
Economic classification
170 441
164 323
167 469
178 648
179 995
182 001
188 520
Compensation of employees
27 699
22 414
20 765
31 964
32 741
34 133
36 032
Goods and services
1 642
2 837
787
325
21
21
21
Transfers and subsidies
1 817
1 016
1 568
1 340
1 340
1 340
1 340
Payment for capital assets
7
65
293
-
-
-
-
Payment for financial assets
201 606
190 655
190 882
212 277
214 097
217 495
225 913
Total
PERFORMANCE AND EXPENDITURE TRENDS
T he Programme’s budget shows an increase of 0.86 per cent from 2022/23 to 2023/24 which is due to the reconfiguration of the Provincial Training Institute and filling of posts. There is a clear dependencey on the availability of funding to ensure that sufficient staff members are employed as well as for infrastructure upgrades, research capacity and ICT systems. The scope and level of current service standards will be impacted by budget allocations, as will the ability to embark on new endeavours.
80
DOTP ANNUAL PERFORMANCE PLAN FOR 2023/2024
Made with FlippingBook - Online Brochure Maker